| The forms are off the walls and curing time has begun. There now will be a period of time before further work is done. 9-1-08 |
| These 4 pictures were taken by Ross Demaggd while flying over the building site. 9-4-08 |
| Basement walls are now backed filled and preparation for pouring the basement floor this coming week. 9-12-08 |
| Basement floor being prepared to be poured. Heat pipes are placed prior to pouring of cement. 9-16-08 |
| Basement floor is poured and let set for two days. 9-17-08 |
| Work begins on building the basement bearing wall, putting it in place and constructing the walls for the utility room. 9-19-08 |
| Installation of floor joists begins and is finished. Good snacks and food were available through-out the day. 9-19-08 |
| On Sunday the sub floor was laid. Work on the stairway to the basement and exterior walls will take place the following week. 9-21-08 |
| Footers have been placed for the walls, construction of the stairway and enclosure for the elevator has begun, cement has been poured for the front porch and garage floor and power has been installed. 9-30-08 |
| Update on the Josh Hoffman home 9-08. |
| All pictures can be seen in larger format by clicking on them. |