Update on the Josh Hoffman home 8-08.
Alaska Excavating begins the excavating 8-26-08
Alaska Excavating excavating and footing placed
and poured by Terry McKinny 8-27-08
Terry McKinney Poured Wall Co. set all the forms for the basement walls and poured the forms
full. This was done with the help of the pumper truck from Cascade Concrete Pumping and
cement from High Grade 8-28-08
All pictures can be seen in larger format by clicking on
them.